As a Product Owner, you must add estimates to your Backlog for a few items. You’d like your team to reach a consensus on several things, and you would also like to incorporate the Fibonacci sequence. Which effort estimation technique should you use?
- The Bucket System
- Affinity Mapping
- Dot Voting
- Planning Poker™
As a Product Owner looking to incorporate the Fibonacci sequence and have your team reach a consensus on effort estimates for backlog items, you should use the “Planning Poker™” technique. Planning Poker™ is a common Agile estimation technique that involves team members assigning story points (often based on the Fibonacci sequence) to backlog items after discussion and consensus-building, making it suitable for your requirements.