As a project manager, you create a critical path for a project. You add up the duration of the tasks on the critical path from the beginning to the end. What type of pass method did you use to calculate the necessary route?
Or
As a project manager, when determining the critical path for a project, you calculate the total duration of the tasks on this path from start to finish. What specific method or approach have you employed to compute the time of the critical route?
Sequential pass
Backward pass
Low pass
Forward pass
The “Forward pass” method is a fundamental technique used in project management to calculate the total duration of tasks along the critical path, which is the longest sequence of dependent activities that determines the project’s overall duration.