During what Scrum event will the Scrum Master ask questions like What has been our average velocity? Who on the team has any upcoming vacations or work conflicts? Who is responsible for what Sprint tasks?
Or
In which Scrum event does the Scrum Master inquire about details such as our historical velocity, any team members’ upcoming vacations or work-related conflicts, and the assignment of responsibilities for Sprint tasks?
- Sprint Retrospective
- Sprint Planning
- Sprint Review
- Daily Scrum
The Scrum Master would typically ask questions like “What has been our average velocity?” and “Who on the team has any upcoming vacations or work conflicts?” during the Sprint Planning event. Sprint Planning is where the team plans the work for the upcoming Sprint, including discussing capacity, estimating tasks, and assigning responsibilities for Sprint tasks. These questions help assess the team’s ability and planning for the Sprint effectively.