Fill in the blank: To determine the __________of a project, list the milestones you must reach in order to meet the project goal on schedule.

Q: Fill in the blank: To determine the __________of a project, list the milestones you must reach in order to meet the project goal on schedule.

or

Q: Complete the blank: Make a list of the milestones you need to hit in order to complete the project on time in order to calculate the __________ of the project.

  • dependencies
  • capacity planning details
  • critical path
  • float time

Explanation:When you want to establish the critical path of a project, you should make a list of the milestones that you need to accomplish in order to fulfill the project objective on time.