You are making time estimates for your project plan. You ask your task expert to estimate how long the task would take if you assume you need to replace your vendor and experience unexpected turnover right before the task begins. Which of the measures involved in “three-point” time estimations are you asking from your task expert?
- Pessimistic time estimates
- Planning time estimates
- Most likely, time estimates
- Milestone time estimates
In your project planning, when you request your task expert to estimate how long a task would take while considering the need to replace a vendor and accounting for unexpected turnover right before the task starts, you are asking for the Pessimistic time estimates in the context of “three-point” time estimations.