You assign someone as consulted in a RACI chart. What is their expected role in the project?

Q: You assign someone as consulted in a RACI chart. What is their expected role in the project?

or

Q: In a RACI chart, you designate someone as consulted. What part in the project do they anticipate to play?

  • To know the final decision on the project
  • To complete the tasks in the project
  • To give feedback to the team
  • To ensure all the work gets done

Explanation:It is not the responsibility of those who have been designated as “Consulted” to complete duties or make final decisions. Rather than that, they provide significant insights or information to the project by providing the team with input, comments, or expertise. A consultation with them takes place before the making of choices or the implementation of activities.